Amcor Paper Mill, Matraville

2008

CLIENT: Amcor
CONTRACTOR: Sapphire Projects

Team2 Architects were appointed to assiat with the design and delivery of a complex substation and switch room for the Amcor Paper Mill.

Anticipating future expansion and upgrades, a number of various design options were investigated to optimise the substation layout incorporating a number of transformer configurations. Detailed co-ordination was undertaken with the consultant team by way of digital 3d modelling of the services and building.